HDB renovation timeline: Tracking progress against key milestones – metrics

HDB renovation timeline: Tracking progress against key milestones – metrics

Frequently Asked Questions

Initial milestones include planning, design finalization, and obtaining HDB renovation permits, typically taking 2-4 weeks.
Hacking and demolition are typically completed within 1-3 days, depending on the scope of work.
Electrical and plumbing works usually take around 5-7 days, depending on the complexity of the design and the size of the HDB flat.
Flooring and tiling works typically take 7-10 days, depending on the area to be covered and the type of materials used.
Carpentry and custom furniture installation can take 2-4 weeks, depending on the complexity and quantity of items.
Painting and finishing works usually take around 3-5 days, depending on the number of coats and the size of the HDB flat.
The final stage includes cleaning, touch-ups, and final inspections, typically taking 1-2 days to complete.